Cheniere Energy expects its Midship gas pipeline in Oklahoma to commence service no earlier than April—six months behind schedule—and for $1.49 billion, roughly $500 million more than expected last January. The company attributed the delay and higher costs to heavy rains in 2Q19 and the discovery of numerous unknown pipelines during construction. Using available surveys and 811 call data, Cheniere expected the 199-mile Midship project to cross about 240 third-party pipelines. Instead, excavation revealed......
 